Bayou Bridge Pipeline Construction Proceeds in Louisiana Community Despite Invalid Permit Ruling

Julie-Dermansky-022
on

Construction of the Bayou Bridge pipeline has continued in and around the Louisiana town of St. James despite a judgeโ€™s ruling that a state agency wrongly issued a permit allowing this oil pipeline to be built without an emergency and evacuation plan for the vulnerable town. A follow-up judgment formalizing the initial ruling came on Mayย 15.

Judge Alvin Turner, Jr.โ€™s decision, first made on April 30, pertains only to the final 18 miles of pipeline, which in full stretches across southern Louisiana, from Lake Charles, near the Texas border, to a railway terminal in St. James, a largely low-income African-American community. Those last 18 miles fall in a region classified as the coastal zone, an area regulated by the Louisiana Department of Natural Resources (DNR), which issued a costal permit for theย pipeline.

St. James Pastor Harry Joseph is dismayed Bayou Bridge Pipeline LLC, a subsidiary of Dakota Access owner Energy Transfer Partners, appears undeterred by the judgeโ€™s order and has continued construction in the coastalย zone.

โ€œWe stood up to an unjust permit and won,โ€ Pastor Joseph said. โ€œThe judge ruled that letting the company build the pipeline without creating an evacuation route for the community is unjust. But the regulators and local officials are doing nothing to stop theย construction.โ€

Ongoing work on the Bayou Bridge pipeline in St. James, Louisiana
Ongoing work on theย Bayou Bridge pipeline in St. James, which falls in the coastal zoneย ofย Louisiana.

Lisa Jordan, a lead attorney with the Tulane Environmental Law Clinic, told me that in her view the company is in contempt of court and the Department of Natural Resources should have stopped the work until the court order to create an emergency plan is followed. The law clinic is representing Pastor Joseph, the Gulf Restoration Network, Atchafalaya Basinkeeper, and H.E.L.P. (Humanitarian Enterprise of Loving People) in the successful lawsuit challenging theย pipeline.

These plaintiffs originally sued the Louisiana Department of Natural Resources because St. James, located along the Mississippi River and surrounded by many recently built oil storage tanks and chemical plants, now has only a single road into and out of the community. Residents say should an emergency result from a pipelineย failure, they would be left without a way to escape.ย Judge Turner agreed with this evaluation in hisย ruling.

In a letter Jordan sent to a lawyer for Bayou Bridge Pipeline LLC, she pointed out that the court ordered that the company provide an effective emergency response and evacuation plan to DNR โ€œprior to the continued issuance of said permit.โ€ She demanded that the company cease construction until the company โ€œcomplies with the courtโ€™s order and DNR has issued a legalย permit.โ€

Bayou Bridge pipeline construction workers in a light rain
Light rain coats equipment in St. James, Louisiana at a Bayou Bridge pipeline constructionย site.ย 

I asked Energy Transfer Partners if it thoughtย continuedย work on the pipeline was going against the court order, but the company did notย respond.ย 

On Friday, May 18, I drove to St. James, pulling off the road to shoot ongoing construction near the end of Burton Lane. As I shot photos in a light rain that evening, pipeline workers photographed me with cell phones. After about 10 minutes, a sheriff came to see what I was doing. I explained that I was documenting the continued construction because the plaintiffs in a lawsuit challenging the pipelineโ€™s permit considered the workย illegal.

After checking my driverโ€™s license and press credentials, the sheriff asked if I had gotten what I needed. I replied that I had and continued on myย way.

Bayou Bridge pipeline construction workers take cell phone photos of photojournalist Julie Dermansky
Pipeline workers taking photojournalist Julie Dermanskyโ€™s picture in St. James as she photographed them working while aย light rain fell on Mayย 18.

Local sheriff pulls up to see what photojournalist Julie Dermansky was doing at the pipeline construction site
Local sheriff pulls up while photojournalist Julie Dermansky is working to see what sheโ€™sย doing.ย 

Jordan also sent a letter to DNR asking the agency to stop the company from working on the pipeline in the coastal zone. โ€œWe are concerned that the DNR is in contempt of court in failing to order Bayou Bridge to cease and desist construction activities until it, and DNR haveย complied with theย Courtย order andย unless and until DNR issues a legal permit,โ€ย the letter states, before asking that the agency take immediateย action.ย 

However, according to DNR, the ongoing work in the coastal zone is still permissible.ย Patrick Courreges, communications director forย the agency,ย explained to me: โ€œBasically, theย judgeโ€™s ruling is not executory โ€” meaning it canโ€™t be fully executed, until either we have decided not to appeal or 30 days from the day the judgment came out have run out, to give us the opportunity toย appeal.โ€

Furthermore, if DNR were to tell the company to stop work before the agency decides whether or not to appeal, or if the 30 days havenโ€™t run out before a decision is made,ย Courreges said,ย โ€œDNR technically doesnโ€™t have a legal leg to stand on.โ€ The agency canโ€™t demand Bayou Bridge stop work before deciding its next move, he said, not without a restraining order or injunction filed against the company. โ€œThey are not breaking the law,โ€ heย said.ย 

At first,ย Pastor Joseph wasย surprisedย thatย constructionย of the pipeline didnโ€™t stop after they won their case, but he sees it as a sign of the times. โ€œIf theย presidentย of the United States can behave as if the lawsย donโ€™tย apply to him,โ€ he mused,ย โ€œwhy should we expect the pipeline company to obey theย law?โ€ย 

Main image: Workers proceed with construction of the Bayou Bridge pipeline in St. James Louisiana.ย Credit: All photos by Julie Dermanskyย ยฉ2018

Julie-Dermansky-022
Julie Dermansky is a multimedia reporter and artist based in New Orleans. She is an affiliate scholar at Rutgers Universityโ€™s Center for the Study of Genocide and Human Rights. Visit her website at www.jsdart.com.

Related Posts

on

New documents show close coordination between the oil major and a coalition of free-market think tanks at a crucial moment in climate diplomacy.

New documents show close coordination between the oil major and a coalition of free-market think tanks at a crucial moment in climate diplomacy.
Analysis
on

Right wing YouTuber Tim Pool is the latest to own โ€˜climate peopleโ€™ with fake facts spouted by a grizzled TV oilman.

Right wing YouTuber Tim Pool is the latest to own โ€˜climate peopleโ€™ with fake facts spouted by a grizzled TV oilman.
on

Critics say the controversial GWP* method โ€“ which New Zealand appears close to adopting โ€“ is โ€œopen to significant abuseโ€.

Critics say the controversial GWP* method โ€“ which New Zealand appears close to adopting โ€“ is โ€œopen to significant abuseโ€.
on

Lord Moynihan of Chelsea, who holds shares in Shell and TotalEnergies, called the green transition a โ€œchildrenโ€™s crusadeโ€.

Lord Moynihan of Chelsea, who holds shares in Shell and TotalEnergies, called the green transition a โ€œchildrenโ€™s crusadeโ€.