In a split decision Thursday, Pennsylvania state regulators allowed the aging Mariner East 1 (ME1) pipeline to resume transporting highly explosive natural gas liquids (NGL), but continued an emergency shut-down of work on a section of a second NGL pipeline, the almost-complete Mariner East 2 (ME2).
The compromise motionย by chairwoman Gladys Brown squeaked by on a 3 to 2 vote at a morning meeting of the state Public Utilities Commission (PUC) in Harrisburg, with dissenting commissioners John Coleman and Norman Kennard supporting an immediate restart of construction on Mariner East 2. Commissioners David Sweet and Andrew Place voted withย Brown.
Coleman and Kennardโs dissent largely parroted the position of pipeline owner Sunoco, now a part of Energy Transfer Partners (ETP), builder of the highly controversial Dakota Access pipeline, as well as the Rover, Bayou Bridge, and many others. ETP pipeline projects have a long record of leaks, shoddy construction practices, and deceptive dealings withย landowners.
In a joint statement, Coleman and Kennard claimed there has been no evidence โthat there is anย immediateย safety threat that warrants halting construction of ME2 and ME2X.โ ME2X is new pipeline that supplements and runs along the same route as ME2.
The PUCโs decision did provide a glimmer of relief for increasingly desperate landowners, residents, school districts, and others within the immediate proximity of the Mariner pipelines โ the so-called โblast zoneโ where an accidental leak could cause a catastrophic explosion. Of particular concern are deep sinkholes that appeared a few months ago in the backyards of suburban homes along Lisa Drive in West Whiteland Township, near an Amtrak railย line.
The PUCโs order addressed at least some of theseย concerns.
โWhile there is insufficient evidence to support a finding that ME1 is being operated unsafely in West Whiteland Township, I do find that there is sufficient evidence to support a finding that the construction on ME2 and ME2X should remain halted until Sunoco meets the requirements that will be imposed by this Motion,โ Brownย wrote
Those requirements include that within 20 days, Sunoco must provide inspection and testing protocols, a comprehensive emergency response plan, and an up-to-date safety training curriculum for employees and contractors โ all of which have been demanded by local residents for years. Sunoco also has to verify that it has the proper state Department of Environmental Protection approvals and permits to continue construction of ME2 andย 2X.
Todayโs action came in response toย a May 24 emergency orderย by Administrative Law Judge Elizabeth Barnes halting use of ME1 and construction on ME2 in West Whiteland Township, where sinkholes hadย developed.
Barnes cited ongoing contamination of drinking water due to horizontal drilling and other work on ME2, sinkholes, and at least three leaks in the last year in heavily populated areas for ME1. All told, the pipelines are blamed for over 100 spills and the contamination of at least a dozen water wells. The project has garnered fines as high as $12.6 million for permitย violations.
The Mariner pipelines carry natural gas liquids like propane, butane, and ethane from the Marcellus shale 350 miles across Pennsylvania forย export to Scotland and other countries where they will be turned into plastic products, most of which would likely be sold in the United States.ย Enormous โDragon Classโย tankers, purpose-built to haul large volumes of NGLs โ especially ethane, the key building block for numerous plastics โ form the final leg of a kind of overseas pipeline. The name โMarinerโ derives from this transoceanicย mission.
Barnesโ order, which relied on evidence presented during two days of hearings, was triggered byย a complaintย filed with the PUC by State Senator Andy Dinniman, a vociferous opponent of the Mariner pipelines. Barnes agreed with Dinniman that the Mariners present โan emergency situation which represents a clear and present danger to life orย property.โ
Critics, as well as Barnes, have noted that unlike many pipelines that traverse the Great Plains or other areas that are largely devoid of people, the entire eastern leg of the Mariner project cuts through a densely populated corridor terminating in the suburbs of Philadelphia โ what Barnes called โhigh consequenceย areas.โ
Dinniman quickly fired back at what he charaterized as an inconsistent and illogical ruling by the PUC.
โI donโt understand why the PUC would affirm some of the public safety issues at stake involving the construction of Mariner East 2 and 2X, but completely ignore others involving Mariner East 1,โ Dinniman said in a statement. โAfter all, thatโs the one that potentially presents the most immediate danger to myย constituents.โ
โThe bottom line is our position has not changed. We continue to have very real and significant concerns regarding the stability of Mariner East 1 โ an 87-year-old pipeline carrying highly volatile natural gas liquids within close proximity of schools, playgrounds, senior care facilities, neighborhoods, a library, a shopping mall, and a railย line.โ
Dinniman said he and his legal team will evaluate what next steps toย take.
Dinniman, the Clean Air Council, and some affected residents have all mounted legal challenges toย Mariner.
Yet another front was opened in the anti-Mariner campaign on June 12, when the Delaware Riverkeeper Networkย filed suitย in federal court to halt ME2. The Riverkeeper Network charged that Sunoco violated the federal Clean Water Act and its state equivalent, the Clean Streams Law, by discharging โsediment laden stormwater to Pennsylvaniaโs waters on numerous occasions,โ resulting in violations of of water quality standards โฆ in various counties across the state ofย Pennsylvania.โ
Sunoco released a statement lauding the restart of ME1, but said โwe are concerned that upholding other aspects of the administrative law judgeโs Order does not follow applicable law and if not corrected brings uncertainty to Pennsylvaniaโs entire regulatoryย environment.โ
The PUCโs restart of Mariner East 1 was quickly condemned by affected residents in Chester and Delawareย counties.
Eric Friedman, who lives with his wife and young son just a few feet from the Mariner pipelines in Glen Mills, Pennsylvania, in Chester County, and is the spokesman for Del-Chesco United for Pipeline Safety, said his group โis disappointed that the PUC Commissioners โฆ voted to overrule their Administrative Law Judge and allow restart of the ancient, leak-prone Mariner Eastย 1.
โThe Commissioners failed to acknowledge the lack of any credible public safety plan or the detailed safety concerns provided to them by the Chester County Commissioners; over one hundred Pennsylvania municipalities; numerous lawmakers from both political parties and at least two large schoolย districts.โ
Friedman also noted the close ties between the PUCโs commissioners and the oil and gas industry, which were detailed inย a recent reportย by the Public Accountabilityย Initiative.
That report found that four of the five commissioners have close professional or financial ties to the oil and gas industry. Commissioner Norman J. Kennard was previously a partner at the law firm currently representing Sunoco on Mariner East. Commissioner David Sweet is also an ex-partner at a law firm that represents Sunoco. Commissioner Andrew Place is a former executive at a major drilling firm, and Commissioner John Coleman is a director at SilcoTek, which provides high-tech protective coatings to the oil and gas industry, theย reportย found.
In their statement opposing todayโs PUC decision, commissioners Coleman and Kennard said the PUCโs Pipeline Safety Division, part of the PUCโs Bureau of Investigation and Enforcement (BIE), is tasked with ensuring safe pipeline construction and operations, and provides โthe Commissionโs boots on the groundโ to protect theย public.
Coleman and Kennard said that the Pipeline Safety Division spent 76 inspection days examining Mariner during 2017 and is pledged to continue this โrigorous inspection scheduleโ throughout 2018. The dissenting commissioners noted that to date, these thorough inspections have yet to find anythingย wrong.
โExactly!โ retorted Friedman. โWhen they shut down ME1, that was BIEโs first-ever enforcement action against a hazardous liquids pipeline. And Sunocoโs abysmal record of continuing accidents in Pennsylvania demonstrates the overall inadequacy of the PUCโs regulatory scheme.โ
Main image: Sunocoย pipeline, Mariner East graphic Credit:ย Chester County Planningย Commission
Subscribe to our newsletter
Stay up to date with DeSmog news and alerts