Investigation: Has Banks Group Illegitimately Commenced Work at the UK's Newest Coal Mine?

authordefault
on

The legitimacy of the โ€˜Bradleyโ€™ opencast coal mine in Durhamโ€™s Pont Valley has been called into question after the operator, Banks Group, appeared to commence work before key planning conditions had beenย completed.ย ย 

Evidence gathered by DeSmog UK suggests that Banks group failed to follow the strict conditions agreed in a specific planning document โ€”Section 106 โ€” agreed between the contractor and Durham County council. The deadline for the mining work to have โ€œcommencedโ€ was 3 June 2018, otherwise the mineโ€™s planning permission would beย void.

Time-stamped photographs show heavy machinery at the controversial site scrapping back vegetation and stripping back soil, stockpiling huge mounds on 14 May 2018 and 18 May 2018 โ€” allowing Banks Group to claim work hadย โ€œcommencedโ€.

However, construction work was still taking place to satisfy key conditions in the Section 106 agreement two weeks after the soil stripping works had begun. This suggests Banks Group had breached its Section 106 agreement, illegitimately commencing work on the UKโ€™s newest opencast coalย mine.

Section 106ย Agreements

Banks Groupโ€™s rush into commencing work at the Bradley site in Pont Valley can be explained by the tricky nature of its planningย permission.

The first application to open a coal mine at the Bradley site was rejected in 1986. A second application was rejected in 2011. But permission was eventually granted in June 2015 to mining company UK Coal following a three-year appealย process.

UK Coal went bust in 2014 following a major fire at the companyโ€™s largest mine in Daw Mill. Banks Group subsequently took on the Bradley mine permission, and announced in January 2018 that it was trying to acquire the land rights to push ahead with theย project.

Planning permission for the Bradley mine under the current license would have ran out on 3 June 2018 had works not commenced, which is why Banks Group rushed to start work at theย site.

Banks Group operates the nearby Shotton and Brenkley coal mines and claims to mine around one million tonnes of coal each year. The Shotton coal mine is situated on the Blagdon Estate and is owned by hereditary peer Matt Ridley, an advisor to climate science denial campaign group, the Global Warming Policy Foundation (GWPF).

Earlier this year, the government blocked Banks Groupโ€™s proposal for a new coal mine near the beauty spot of Druridge Bay in Northumbria. Campaignersโ€™ calls for the Communities Secretary to block the Bradley mine in Pont Valley have so far beenย ignored.

According to the planning advisory service (PAS), an organisation that provides support to local authorities on planning matters, Section 106 agreements โ€˜are a mechanism which make a development proposal acceptable in planning terms, that would not otherwise beย acceptableโ€™.

If Banks Group is guilty of breaching its obligations under the Section 106 agreement than the punishment could be severe. Durham County Council has the power to issue an injunction against any party that breaches theย agreement.

On 18 May 2018, Banks Group declared it had commenced work at the mine. But evidence uncovered by DeSmog UK suggests a number of conditions under the Section 106 agreement may not have been met, including finishing the access road to theย site.

Durham County Council refused to answer DeSmog UKโ€™s detailed questions about the apparent problems regarding the satisfaction of a number of planning conditions. Banks Group pointed DeSmog UK to a council statement saying the authorities were satisfied the conditions had beenย met.

The lack of action taken by Durham County Council to regulate the works being undertaken by Banks Group has not gone unnoticed by campaigners opposed to the open-castย mine.

Anne Harris from the Coal Action Networkย said;

โ€œDurham County Council and the Planning Inspectorate gave reassurances during the planning process that any company extracting coal from this land would be held to the conditions of planning laid out in the planning approval and the Section 106ย agreement.โ€

โ€œThis was a lie, no significant action has been taken against the mining company since it broke the Section 106 agreement by stripping soil prior to completing the accessย road.โ€

MPย Questions

Caroline Lucas, MP for Brighton Pavilion and current co-leader of the Green Party, has also questioned the justification for allowing Banks Group to continue with its proposed open-cast coal mine in the Pontย Valley.

On 18 June 2018, Lucas issued a written parliamentary question to the Ministry of Housing, Communities and Localย Government.

Lucas asked the Secretary of State to clarify,ย โ€œwhether any errors were made in the appeal decision on planning permission for the proposed Bradley open-cast coal mine in Countyย Durham.โ€

The question remainsย unanswered.

This isnโ€™t the first time Lucas has written to Communities Secretary James Brokenshire about the contentious coal mine. On 14 May 2018 Lucas asked the Secretary ofย state:

โ€œwhat assessment he has made of the potential effect of the proposed โ€˜Bradleyโ€™ open-cast coal mine in Pont Valley, County Durham on the UK meeting its carbon reduction targets in the Climate Change Actย 2008.โ€

Three days later on the 17 May, Jake Berry, the Parliamentary Under-Secretary within the Department for Housing, Communities and Localย replied:

โ€œThe Secretary of State is currently considering requests to revoke the planning permission, granted on 3 June 2015, for surface coal mining at the Bradley site. These requests are being considered in the light of the current policy on revocation. I am therefore unable to comment on any aspects of this proposal as to do so is likely to beย prejudicialโ€ฆโ€

The outcome and timing of the Secretary of Stateโ€™s review is crucial, as Banks Group is continuing work in theย meantime.

The lack of a decision by James Brokenshireโ€™s office has angered some in the local community. Local resident June Davison said the delays were causing residents distress. She told DeSmog UK:

โ€œItโ€™s sickening that someone with the power to influence the lives of so many people, can sit on a decision for nearly 4 months. James Brokenshire and his team are fully aware of the urgency of our request and still have not responded one way or theย other.โ€

Planningย Conditions

Concerns have been flagged up in recent weeks by the local community that Banks were rushing ahead and it was unclear if key planning conditions that would enable works to commence had been properlyย finalized.ย 

To assess the current situation on the ground, DeSmog UK visited the site on 20 Juneย 2018.

On that day, there were no visible noticeboards other than security signs, metal fencing lay strewn on the floor, the street lighting to the all-important access road was yet to be finished and an excavator was working away on top of a huge soil mound, perilously close to the publicย pavement.

Significantly, the access road inside the site had not been completed, so vehicles were parked on a dirt patch just inside theย gates.

A short distance from the proposed mine is the village of High Stables, home to a community that has been valiantly fighting plans for an open-cast coal mine for over 30 years. From here you can follow the footpaths into the Pontย valley.

A short distance up the picturesque footpath, near the perimeter of the future opencast mine there are mounds of black soil, more Banks group security signage and gaps in the boundary fencing that you could drive a busย through.

In the distance enormous tipper trucks were rumbling along tracks cut into the valley for transporting the top soil around theย site.

The Planning Inspectorateโ€™s โ€˜appeal decisionโ€™ published on the 3 June 2015 reconfirmed the need for Banks to abide by the planning conditions proposed by Durham County Council including those required to be in place before worksย commence.

The 79 conditions, detailed in appendix A of the planning inspectorateโ€™s decision document detailed the strict processes that Banks needed to follow from pre-commencement stage all the way through to the aftercare and siteย restoration.

This includes requirements to provide details of the site fencing (condition 5H), site notice board (5N), and the layout of the site compound (5L). Further conditions range from the dust control (5D) to Noise monitoringย (5B)

DeSmog UK has summarized some of the key planning conditions that needed to be discharged before Banks group commenced work, many of which do not appear to have been fullyย satisfied:

When visiting the site, DeSmog UK identified issues regarding the notice boards, site compound, fencing conditions, dust, andย pond.

Following the site visit, DeSmog UK contacted Durham County Council and asked the authority to comment on the status of the planning conditions with particular emphasis on the status of the highway works and a range of other requirements ranging from soil management, dust control and archaeological surveys to tree protection, wheel washing facilities and site noticeย boards.

Durham County Councilย replied:

โ€œIโ€™ve spoken to our planning team and Iโ€™m afraid it is not possible to provide this information within your deadline. We would suggest that you submit it as an FOI. I can forward this on to our FOI team if you would like meย to.โ€

DeSmog UK has now submitted the FOIย requests.

BBC research shows that requesting sensitive information through FOIโ€™s is riddled with problems, with authorities using a variety of tactics to avoid disclosing crucial information. And the council legally has up to 20 working days to respond โ€” providing Banks Group with a further month to continue workย unchallenged.

Stuart Timmiss, Durham County Councilโ€™s head of planning and assets nonetheless told DeSmog UK:

โ€œWe are content that the works currently being carried out on site are in accordance with the planningย permission.โ€

He did not provide any detailed answers regarding the evidence of potential breaches provided by DeSmog UK, or further detail on how the Council came to be satisfied that the conditions had beenย met.


Credit: June Davison

Credit: Russellย Scott

Main Image Credit: Russellย Scott

Related Posts

on

The decision to allow Novatek to attend the flagship conference was described as โ€œdisappointingโ€ and โ€œdisturbingโ€ by campaigners.

The decision to allow Novatek to attend the flagship conference was described as โ€œdisappointingโ€ and โ€œdisturbingโ€ by campaigners.
on

Badenochโ€™s leadership campaign was part-funded by a board member at one of the worldโ€™s largest fossil fuel companies.

Badenochโ€™s leadership campaign was part-funded by a board member at one of the worldโ€™s largest fossil fuel companies.
Analysis
on

The Conservative leader, who attacked โ€œradical green absolutismโ€ in a Washington DC speech, recently met with a host of influential anti-climate figures.

The Conservative leader, who attacked โ€œradical green absolutismโ€ in a Washington DC speech, recently met with a host of influential anti-climate figures.
on

Campaigners raise concerns over โ€˜alarmingโ€™ potential conflicts in the powerful political grouping.

Campaigners raise concerns over โ€˜alarmingโ€™ potential conflicts in the powerful political grouping.