Fracking Company Cuadrilla Breached Environmental Regulations Seven Times in 10 Months

authordefault
on

Shale gas exploration company Cuadrilla has breached environmental permits multiple times and failed to disclose full details of technical issues at its Lancashire site, a DeSmog UK investigation hasย found.

The company breached its environmental permits seven times in 10 months in 2017, analysis of Freedom of Information requests and publicly available Environment Agency Compliance Assessment Reportsย shows.

DeSmog UKโ€™s investigation also uncovered a survey commissioned by the company that identified faults with a protective membrane, despite the company telling local residents it had never neededย repairs.

British Geological Survey data also shows Cuadrilla experienced six tremors within eight days after it commenced fracking in October 2018. Fracking had to be halted for a second time after a magnitude 0.8 tremor onย Friday.

The investigation also revealed that the Environment Agency, which is tasked with ensuring the site operates within agreed environmental parameters, encountered problems with air pollution monitoring at the site due to faultyย equipment.

Campaigners told DeSmog UK that the findings gave them โ€œno confidenceโ€ that the government could implement promised ย โ€œrobustโ€ regulations, as ministers seek to encourage fracking across theย country.

Academics told DeSmog UK that the findings show the need for Cuadrilla and regulatory authorities to share more information with independent experts to avoid speculation that the company is trying to hide unsafeย practices.

Cuadrilla told DeSmog UK that it acknowledged the โ€œminorโ€ breaches, but maintained its practices were safe for the environment. A spokesperson for the companyย said:

โ€œWe accept there have been minor and non-significant breaches and these are already a matter of public record. It is important to note that Cuadrilla proactively reported to the Environment Agency in line with our permits. In all cases there was no negative impact on the environment and there has been no action against Cuadrilla by the Environmentย Agency.โ€

Breaches

The Environment Agency reports state that the significance of the breaches DeSmog UK found ranged from โ€œnot regarded as a serious issueโ€ to issues where โ€œimprovements are requiredโ€ to comply with theย law.

A spokesperson for the Environment Agency told DeSmog UK that to date it had issued Cuadrilla with warnings for five non-compliances at the site. DeSmog UK found evidence of seven breaches among the Environment Agencyโ€™s assessmentย reports.

The breaches relate to how Cuadrilla handles waste on site, manages water, and takes responsibility for waste once it has left theย site.ย 


Breach 1 | 02 March 2017 | Unpermitted release into a nearby Brook and โ€˜inadequateโ€™ managementย systems

The Environment Agency warn Cuadrilla over โ€œtwo incidents involving the discharge of surface water containing siltโ€ into the nearby Carr Bridgeย Brook.

The first incident occurred on the 27 February 2017 and was caused by โ€œa surface water managementย problemโ€.

The second incident was caused by an escape of silt-containing water from Cuadrillaโ€™s wellย pad.

The EA also warned Cuadrilla that its water management systems were found to be โ€œinadequateโ€ and required โ€œimprovementโ€ to prevent escaping water from causingย pollution.

Breach 2 & 3 | 14 June 2017 | Unpermitted discharge of โ€˜contaminated surfaceย waterโ€™

On the 14 June 2017, the Environment Agency inspected the Preston New Road well pad. During the site inspection, Cuadrilla informed the regulator of an unpermitted โ€œdischarge of silt contaminated surface waterโ€ from the frackingย site.

According to the Environment Agencyโ€™s report dated 6 October 2017, โ€œthe escape of silt contaminated surface water had occurred through an electrical conduit inside an interceptorย chamberโ€.

The report also noted that the contaminated waste โ€œspilled onto ground which spread across landโ€ and eventually ended up draining into a nearby water tributary, the Carr Bridgeย Brook.

The EA subsequently conducted its own tests and did not identify any pollution caused by this incident and concluded that โ€œany impact on the tribuary (sic) of Carr Bridge Brook would have beenย minimalโ€.

Cuadrilla were warned for breaching two permit conditions: the first for failing to notify the regulator of the event and the second for the unpermittedย leak.

Breach 4 | 1 August 2017 | Failure to store wasteย correctly

On this occasion, the Environment Agency discovered the firm was failing to store its drilling waste correctly. Drilling cuttings are the waste dirt and broken bits of rock removed from a borehole as part of the underground drilling process, and may contain naturally occurring radiation andย chemicals.ย 

The inspection report notes that Cuadrilla was using standard metal skips to store the โ€œspoiltโ€ drilling waste. These, it found, were not โ€œhydro tested for leaksโ€ or โ€œappropriately certified for integrityโ€ as required under the agreed waste management plan, which classifies spoiled drilling waste asย hazardous.

This non-compliance, the EA warned, could โ€œforeseeably result in a minor environmental effectโ€. โ€œThis is not regarded as a significant issueโ€, the reportย states.

The Environment Agency ordered the firm to use the correct storage containers and conduct both weekly visual integrity checks and annual thicknessย testing.

Breach 5 & 6 | 23 November 2017 | Regarding site drainage and the prevention ofย emissions

These breaches were identified on an independent database. However, the Environment Agency is yet to release detailed assessment reports on the breaches. The only details available currently are that the breaches relate to criteria โ€œB3 Infrastructure โ€“ site drainage engineeringโ€ and โ€œB1 Infrastructure โ€“ engineering for prevent ofย emissionsโ€.

Breach 7 | 7 December 2017 | Use of unpermitted site for storage of waste on at least 22ย occasions

Cuadrilla broke the law and received a formal warning from the EA on the 25 Julyย 2018.

The warning letter outlined how Cuadrilla had not taken reasonable measures to prevent extractive waste being temporarily stored at an unpermittedย site.

It also stated that Cuadrilla had used non-unique consignment notes, providing incorrect name for the waste produce, incorrect consignee name, incomplete information about the wasteโ€™s relevant chemical components with their concentrations and wrong hazardย codes.

The 22 separate occasions that Cuadrilla stored waste at an unpermitted location were observed overย a period of three months between 7 March 2017 and 9 Marchย 2018.

The assessment report does note, however that the Environment Agency โ€œcan conclude that overall waste drilling muds and cutting were treated and disposed in line with sound waste managementย practicesโ€.

The Environment Agency gave Cuadrilla notice that โ€œfurther checks will be carried out within 3 weeksโ€ to check the company had addressed theย issues.


A spokesperson for the Environment Agency told DeSmog UK that โ€œoil and gas operators must meet the highest environmental standards which are set out inย law.โ€

The agency said minor non-compliances are not unusual after site inspections and audits, and that it works hard with developers to addressย these.

A spokesperson for Cuadrilla told DeSmog UK that it continued to work with the Environment Agency to ensure it complied with environmental standards. A spokespersonย said:

โ€œIn terms of the specific breaches, they are publically reported by the EA.โ€

โ€œEarlier this year, the EA completed a comprehensive waste management audit which included the contributions made by our contractors and sub-contractors. The EA concluded that overall they were satisfied that the audited waste streams were removed from Preston New Road to appropriate waste facilities in line with good practice. We are confident that all waste streams have been treated and continue to be treated fully in accordance with the permits inย place.

โ€œThe EA did note a number of minor non-compliance issues, although none impacted on how waste should have been or was treated. We have addressed theseย issues.โ€

Faulty Air Monitoringย Equipment

The Environment Agency has had some problems monitoring all aspects of the site,ย however.

The Environment Agency deployed a โ€˜mobile monitoring facility (MMF)โ€™ to Cuadrillaโ€™s Preston New Road fracking site in August 2017 with the purpose of carrying out background level monitoring of different types ofย pollutants.

The regulator publishes the data from the MMF in a monthly air quality monitoring report. The September 2018 report notes numerous problems with the monitoringย equipment:

Date

Pollutantsย recorded

Issue

23 August 2018 โ€“ 9 Septemberย 2017

benzene, toluene, ethylbenzene and xylene (BTEX)

No BTEX data recorded between these dates โ€˜due to technical problems with theย instrumentโ€™

6 March 2018 โ€“ 6 Aprilย 2018

particulates (PM10)

No data recorded between these dates. The measuring equipment was switched off โ€˜due to complaints about noise coming from the monitoring stationโ€™ by a localย resident

6 March 2018 โ€“ 12 Aprilย 2018

particulates (PM2.5)

No data recorded between these dates. The measuring equipment was switched off โ€˜due to complaints about noise coming from the monitoring stationโ€™ by a localย resident

26 April 2018 โ€“ 1 Mayย 2018

Methane (CH4)

No Methane data recorded between these dates โ€˜due to technical problems with theย analyser.โ€™

29 June 2018 โ€“ 6 Julyย 2018

benzene, toluene, ethylbenzene and xylene (BTEX)

No BTEX data recorded between these dates โ€˜due to the instrument being removed forย servicingโ€™

The Environment Agency said equipment may occasionally be offline for routine maintenance orย repairs.

Membrane Defects

Cuadrilla also appears not to be disclosing the full details of some environmental issues at theย site.

A protective geomembrane layer helps to prevent contamination below the Preston New Road well pad. But a survey commissioned by Cuadrilla appears to identify defects with the layer โ€” contradicting statements made in public by theย company.

At a Community Liaison Group meeting between Cuadrilla and the local community held on September 10 2018, the companyโ€™s technical director Mark Lappin was questioned about the โ€˜integrityโ€™ of the membrane layer. The meeting minutesย note:

โ€œHas the existing membrane been replaced or โ€˜patched upโ€™? Mark Lappin explained that the integrity of the existing membrane remains and has not needed to be restored orย repaired.โ€

A report sent by Cuadrilla to the Environment Agency seems to contradict Cuadrillaโ€™s statement,ย however.

A redacted copy of a report titled โ€˜Geomembrane leak detection surveyโ€™ for the Preston New Road well pad, obtained through a Freedom of Information request, identified โ€œfive defects in the liner systemโ€ during a survey that took place between 20 June and 29 Julyย 2017.

The purpose of the report was to โ€œlocate any damage to the placed geomembraneย linerโ€.ย 

The report is dated August 2017 was commissioned by Cuadrilla and emailed to the EA by Cuadrilla on the 7 Septemberย 2017.

Professor Richard Davies, a petroleum geologist at Newcastle University, told DeSmog UK that the data was insufficient to show โ€œwhether anything serious isย wrongโ€.

However, he said it did show that โ€œmembranes arenโ€™t a fail-safe mechanism for sealing the well-pad. Itโ€™s showing itโ€™s not a perfectย solution.โ€

The defects were subsequently repaired byย Cuadrilla.

A spokesperson told DeSmog UK:

โ€œThe geomembrane was tested in 2017 prior to drilling operations getting started. The test highlighted some minor repairs were required and these were carried out. It has maintained full integrity since that time including testingย post-drilling.โ€

Tremors

Cuadrilla has had some well-publicised issues with small tremors since it started fracking in October 2018, including six tremors within the first nine days of fracking. On Friday, it halted fracking for a second time after a magnitude 0.8 tremor, which registers as a โ€œred lightโ€ on the governmentโ€™s traffic lightย system.

Red light tremors of 0.5 magnitude or above require the company to suspend frackingย immediately.

Records show that there have been multiple and frequent tremors since Cuadrilla startedย fracking.

Cuadrilla announced on the October 15 2018 that it had commenced with fracking at its Preston New Road well pad after a last-ditch injunction to stop the process had failed to halt theย operator.

By the October 18 2018, the British Geological Survey (BGS) picked up three small tremors within very close proximity of Cuadrillaโ€™s horizontally drilledย well.

The three seismic events ranged in magnitude from -0.2 to -0.8 ML.

At this strength Cuadrilla were still within the Oil and Gas authorityโ€™s (OGA) โ€˜greenโ€™ zone on the seismicity traffic light system so fracking was allowed โ€œproceed as plannedโ€.

Three more earthquakes followed on the 19, 20 and 23 October. The magnitude of the tremors increased up to 0.4ML and into โ€˜Amberโ€™ zone on the traffic light system, resulting in Cuadrilla having to โ€œproceed with cautionโ€. The tremor that occurred on the October 19 2018 was registered by the BGS only 15 minutes after a frack test had been completed byย Cuadrilla.

The largest of the six tremors occurred on the 23 October 2018 at 2.45pm while Cuadrilla were actively fracking at PNR. Cuadrilla noted;

โ€œThe highly sensitive monitoring systems at and around Cuadrillaโ€™s shale gas exploration site in Preston New Road have detected a seismic event within the companyโ€™s operational area (approx 4.8km3) of 0.4ML (Local Magnitude) this afternoon while hydraulic fracturing operations wereย ongoing.โ€

As a result of the Amber warning quake being registered, Cuadrilla took the decision to suspend operations for theย day.

Date

Time (UTC)

Magnitude

Region

23/10/18

14:45:32.5

0.4

Blackpool,ย Lancashire

20/10/18

03:44:01.4

0.0

Blackpool,ย Lancashire

19/10/18

13:20:48.5

0.3

Blackpool,ย Lancashire

18/10/18

23:44:41.9

-0.3

Blackpool,ย Lancashire

18/10/18

22:54:46.8

-0.8

Blackpool,ย Lancashire

18/10/18

15:48:53.6

-0.2

Blackpool,ย Lancashire

Source:ย earthquakes.bgs.ac.uk

Professor David Smythe, a geologist and Emeritus Professor of the University of Glasgow, who is a prominent critic of the fracking industry, told DeSmog UK:

โ€œIt is normal for all these tiny tremors to be recorded, if a dedicated temporary seismic array is in place, as it is at Preston Newย Road.โ€

โ€œEarthquakes below magnitude of two are not normally felt by humans, and are unlikely to cause any surface damage. Each increase of one unit on the scale means about 30 times more energy isย released.โ€

โ€œIt is difficult to convert a given magnitude into damage or noise, because it depends on how deep the earthquake is. But in round terms, tremors of under a magnitude of three in the Fylde might be felt (as in a heavy lorry going past your door), but will not doย damage.โ€

However, Smythe has previously expressed concerns that โ€œeven after nine years in the Fylde, to understand theย geologyโ€.

โ€œThe problem for Cuadrilla is that if it now carries on regardless after just five daysโ€™ fracking, bigger earthquakes are likely to beย triggeredโ€.

Smythe says he is concerned that the โ€œstrong impression is that Cuadrilla is once again trying to hide its own technicalย incompetenceโ€.

Itโ€™s a viewed shared by local campaigners, who have been fighting the development forย years.

Miranda Cox, a local councillor and prominent anti-fracking campaigner, who sits on the Community Liaison Group, told DeSmog UK she was โ€œfrustrated withย communicationโ€.

โ€œDissemination of information can be shrouded in industry language and is at times, obtuse. Questions are asked of Cuadrilla and the regulators regarding breaches and other issues; frequently these areย deferred.โ€

โ€œPublic scrutiny of the site and regulators is keeping the focus on lapses of safety and good practice. The authorities whose remit is to keep us safe, are under-resourced andย understaffed.โ€

โ€œThe number of issues encountered so far at this one site is indicative of what is to come. If this industry is to become commercially viable and is rolled out across the country, I have absolutely no confidence that the โ€˜robust regulationsโ€™ promised will everย emerge.โ€

Cuadrilla said it was aware of the tremors, and that these were to be expected. A spokespersonย said:

โ€œOf course we are aware of the series of tiny micro seismic events which have been recorded by the British Geological Survey (BGS) since we began hydraulic fracturing operations on Octoberย 15.โ€

โ€œCuadrilla and all the regulators working with us at the exploration site at Preston New Road were expecting micro seismicity to occur as we are hydraulically fracturing shale rock. These events are tiny movements being detected by sophisticated monitoring equipment around theย clock.

โ€œEverything is working as it should and being reported appropriately as part of the Oil and Gas Authorityโ€™s traffic light system. Weโ€™re comfortable that these micro-seismic events, even the one recorded on Friday, are far below anything that could be felt at surface or cause damage orย harm.โ€

Newcastle Universityโ€™s Professor Davies said Cuadrilla needs to share as much data as possible if it is to overcome speculation about the safety of its activities. He told DeSmog UK his research group was being โ€œkept one step away fromย itโ€.

โ€œWeโ€™re not getting enough information to be able to fully assess the impacts of frackingโ€, heย said.

โ€œThe bottom line is weโ€™re getting quite a lot of information. And itโ€™s difficult to work out what is important and what isnโ€™t. So there areย risks.โ€

โ€œIs this leakage tiny and doesnโ€™t contain any toxic materials, or is it more significant than that? We just donโ€™tย know.โ€

โ€œItโ€™s pretty obvious from the US example that where thereโ€™s a lack of information it leads to suspicion and a lack of trust. And I think a lot of the issues around fracking are related to a lack ofย trust.โ€

Related Posts

on

Major oil and gas firms are being represented by lobbyists that have given more than ยฃ300,000 in support to Keir Starmerโ€™s party.

Major oil and gas firms are being represented by lobbyists that have given more than ยฃ300,000 in support to Keir Starmerโ€™s party.
on

New documents show close coordination between the oil major and a coalition of free-market think tanks at a crucial moment in climate diplomacy.

New documents show close coordination between the oil major and a coalition of free-market think tanks at a crucial moment in climate diplomacy.
Analysis
on

Right wing YouTuber Tim Pool is the latest to own โ€˜climate peopleโ€™ with fake facts spouted by a grizzled TV oilman.

Right wing YouTuber Tim Pool is the latest to own โ€˜climate peopleโ€™ with fake facts spouted by a grizzled TV oilman.
on

Critics say the controversial GWP* method โ€“ which New Zealand appears close to adopting โ€“ is โ€œopen to significant abuseโ€.

Critics say the controversial GWP* method โ€“ which New Zealand appears close to adopting โ€“ is โ€œopen to significant abuseโ€.